Illinois Department
of Transportation
Date 10/8/01
Contractor United Paving & Construction, Inc./
United Asphalt Supply, Inc.
^ addition
I recommend that an ~ extension be made ®to
^ deduction ^ from
Request for Approval
of Change in Plans
County Fulton
Road District or Municipality Canton
Section 00-01000-00-GM
Request No. 1
the above contract. .
Between Station and Station a net length of 1184'
(Do not fill in unless a change in length is involved)
The estimated quantities are shown below and the contractor agrees to furnish the materials and do the work at the contract
unit prices. Show station location for major items.
Items Additions Deductions
4. Bituminous Hot Mix Sand Seal Coat Modified
136.7 Ton ®$53.60 $7,327.12
See attached s read sheet for locations -widths, len ths, and uantities.
Since we will have a net deduction for rime no rime was added to
this chap e.
Totals $7,327.12
Net Change $7,327.12
addition
Total net ^ deduction to date $ $7,327.12 which is 3.12 % of Contract Price
BLR 6301 (Rev. 12/97)
State fully the nature and reason for the change The City found it necessary to add these locations. Locations 70 ~ 71
due to condition of roadway in need. Locations 14C & 16A were contigious with existing locations and were determined
also in need.
When the net increase or decrease in the cost of the contract is $10,000 or more or the time of completion is increased or
decreased by 30 days or more, one of the following statements shall be checked.
~( The undersigned determine that the circumstances which necessitate this change were not reasonably foreseeable
at the time the contract was signed.
^ The undersigned determine that the circumstances which necessitate this change were not within the
contemplation of the contract as signed.
^ The undersigned determine that this change is in the best interest of the local agency and is authorized by law.
Signed Signed
Highway Commissioner unicipal Officer
Mayor
Title of Municipal Officer
Date
Date
Approved Recommended
County Engineer
Date
Note Make out separate form for change in length quantities.
Give net quantities only.
Submit 3 copies of this form to District Engineer (4 copies for road district).
If plans are required attach 3 sets.
Approved
District Engineer
Date