HomeMy WebLinkAboutResolution #409~•«F C
~~
~~~~
~~~
RESOLUTION DIRECTING EXECUTION OF
AGREEMENT WITH CITY OF BUSHNELL,
Mc~ONOUGH COUNTY, ILLINOIS,
WHEREAS, City of Bushnell, County of McDonough, State
of Illinois, has requested City of Canton, County of Fulton,
State of Illinois, to authorize said City of Bushnell to
locate, construct, operate, repair and maintain a gas
transmission Line in certain streets, alleys and public
placed of City of Canton and for the compensation and under
terms and conditions all as more fully set forth in an
Agreement tendered in regard thereto, by letter dated
June 2, 1965, a copy of such Agreement being hereto referred
to and incorporated herein by reference thereto, and
WHEREAS, said Agreement has been examined by this City
Council and in terms, words and figures is satisfactory to
this City Council and is deemed desirable and advantageous
for this City and its inhabitants,
NOW, THEREFORE, BE IT RESOLVED, by the City Council of
the City of Canton, County of Fulton, State of Illinois,
that said Contract referred to i.n the preamble of this
Resolution be and it hereby is approved and the Mayor and
City Clerk be and they hereby are authorized and directed
to execute the same for and on behalf of City of Canton,
County of Fulton, and State of Illinois, all in manner and
form as required by law.
REX LOMAX " JOHN J. LYONS Jr.
City Clerk
Mayor
CITY OF BUSHNELL
Office of City Clerk
BUSHNELL, ILLINOIS
June 1, 1965
Pr(ayor and City Council
of-the City cf Canton
Canton, Tllinois
Dear P,~ayor and Council;
For and on behalf of the Citv cf ~?ushnell, the undersigned
requests that your Honorable Body officially grant permission
to the City of Bushnell to lay a ~?as transmission line in the
streets and alleys of your City pursuant to the agreement hereto
attached.
Your kind cooperation in this matter will indeed be a;~preciated
by the City of Bushnell. Thanking you, we remain
Respe ctfully yours,
C IT`r C--F~BUSfi~TELL ..
~ JoYS~ J . " T~on~",- ~r . , Tzlayo r
Fn c .
THIS AGREEMENT made and entered into this day of
June, A. D., Ig65 by and between CITY OF BUSHNELL, McDonough County,
State of Illinois, a Municipal Corporation, hereinafter referred
to as "Party of the First Part" and CITY OF CANTON, County of
Fulton, State of Illinois, a Municipal Corporation, hereinafter
referred to as "Party of the Second Part";
WITNESSETH:
WHEREAS, Party of the First Part is engaged in the
improvement of its Municipal (has Utility, a portion of which
improvement includes the construction of a gas transmission line
from the gas utility of the Party of the First Part to a point of
connection on the pipeline of Panhandle Eastern Pipe Line Company
within the corporate area or without such corporate area of the
Party of the First Part in either event being adjacent to the east
border of such corporate area; and
WHEREAS, in the construction of said gas transmission
line by Party of the First Part it is necessary and advisable that
the Party of the First Part construct a gas transmission line
through the corporate area of the Party of the Second Part with
such line located on streets, alleys and public places of said
Party of the Second Part all as more fully delineated on a plat
hereto attached and made a part of this contract; and
WHEREAS, Party of the First Part has requested that the
Party of the Second Part grant it authorization to locate, con-
struct, operate, repair and maintain said gas transmission line
through the corporate boundaries of the Party of the Second Part
at the location as set forth on said plat hereto attached and
sub,~ect to the certain conditions hereinafter set forth and Party
of the Second Part is willing so to authorize Party of the First
Part.
NOW, THEREFORE, the parties hereto agree as follows,
for and in consideration of the mutual covenants and agreements
hereinafter contained:
- 1 -
1. Party of the Second Part hereby grants
authorization and permission to the Party of the Second Part to
locate, construct, operate, repair and maintain a six inch (6")
gas transmission line through the corporate territory of the
Party of the Second Part and on the route and all as designated
on the map hereto attached and made a part hereof, subject
however to compliance with the terms and conditions and agreements
of the Party of the First Part hereinafter set forth.
2. Party of the First Part covenants and agrees
that in constructing said Gas Transmission Line the same shall
be constructed as Follows:
(a) The gas transmission line shall be
constructed in accordance with plans and specif ications prepared
by Warren & VanPraag, Inc., Consulting Engineers, Decatur, Illinois
dated
and subject to the approval of the City
Engineer of the Party of the Second Part.
(b) The work shall be performed by a bonded
contractor. The contractor, in addition to providing a one hundred
percent performance bond to the Party of the First Part, shall
provide a bond in the amount of One Thousand Dollars to the Party
of the Second Part to insure proper clean-up after completion of
construction.
(c) During construction of the gas line, the
contractor shall proceed as follows:
(1) Materials delivered on the sides of
the street for use on the project shall be placed in such a manner
as to cause the least inconvenience to property owners and to the
general public. Driveways, streets and fire hydrants are not to
be obstructed at any time by the said materials. Pipe placed on
the side of the streets shall be installed within twenty-four
hours after delivery to the construction site except where con-
struction is delayed by weather conditions or other causes beyond
the control of the contractor.
- 2 -
(2) No street, driveway or alley
shall be completely obstructed during construction of the gas
line without permission of the Party of the Second Part. Travel
upon the streets, or upon any intersecting street or alley shall
not be hindered or inconvenienced needlessly.
(3) Not more than fifteen hundred feet
of trench shall be open at any one time. Suitable barricades and
lights shall be installed where required to protect the public
from the open trenches.
(~) All poles, trees, shrubbery, fences,
sewer, water, gas and electric lines shall be supported and pro-
tected from injury by the contractor during construction of the
gas line.
(5) Where practicable all crossings
under streets, driveways and sidewalks shall be made by boring
under the crossing. Where driveways, sidewalks or street surfaces
are cut, they shall be replaced as near as possible to their
original condition. Where sidewalks or driveways are cut, the
entire section to the nearest construction form shall be replaced.
(6) The gas line shall be constructed of
welded polyethylene coated steel pipe with suitable cathodic
protection to prevent corrosion.
3. Repairs and maintenance of said gas trans-
mission line, after its location and construction as of aresaid,
shall be subject to such reasonable rules, regulations and
specific permits as may have heretofore been, or hereafter,
established by the Party of the Second Part applicable to repair
and maintenance of underground gas mains or lines generally in the
corporate territory of the Party of the Second Part.
~. Party of the First Part covenants to pay to
the Party of the Second Part, out of the revenues from its
municipal gas utility, the annual sum of
Dollars for such authorization by Party of the Second Part during
-3-
the term of this authorization as hereinafter set forth, such
payment to be made in lieu of taxes and as consideration for the
authorization granted and on tY~e 1st day of each year in advance
during the term of this agreement.
5. Parties hereto mutually agree that the term
of this authorization shall be for a period of thirty-five (35)
years commencing from the date of the execution of this Agreement,
unless such term be hereafter extended by the Party of the Second
Part.
6. Party of the First Part covenants and agrees
that it will not serve or offer to serve any consumers within
the corporate boundaries of Party of the Second Part.
7. This agreement shall be in full force and
effect, and shall be binding upon, and the benef its hereof shall
enure to, the respective successors and assigns of the parties
hereto.
IN WITNESS WHEREOF, the parties hereto have executed
two copies of this Agreement each of which shall be considered
as a duplicate original, all pursuant to the authorization granted
by resolutions of the respective councils of the parties hereto.
CITY OF BUSHNELL, McDonough County, Illinois
BY
Its Mayor
ATTEST:
Its City Clerk
CITY OF CANTON, Fulton County, Illinois
BY:
Its Mayor
ATTEST:
Its City Clerk
-4-