Job No: 234-03055 Sec. 03-00000-00-GM
to 12/31/2003 Municipality Canton
Estimated Cost of Maintenance Operations
Material. Eauioment or Labor
Maintenance Operation
(No. -Description -Total Quantity)
Item and Specification Quantity
and Unit Unit
Cost
Cost Operation
Cost
* Fee Grouo
CONTRACT MAINTENANCE
*
1. Bit. Hot Mix Sand Seal Coat (IV) Bit. Materials Prime Coat 2,871 Gal. $1.05 $3,014.55
(64,384 Sq. Yd.) Bit. Hot Mix Sand Seal Coat (Mod.) 4,176.5 Ton $57.00 $238,060.50 $241,075.05
GENERAL MAINTENANCE
2. Drainage Repairs (III) P.C.C. Curb & Gutter M6.05 80 Foot. $39.00 $3,120.00
HemIOCk Street Fabric 1 Roll $325.00 $325.00 $3,445.00
3. Sidewalk Repairs (II-)
Ave. A by Bank Sidewalk 660 Sq. Ft. $4.25 $2,805.00
Curb 63 Foot $39.00 $2,457.00 $5,262.00
4. Street Sweeping (II) Cargo 7000 Elgin Sweeper (Public) 659 Hours $45.55 $30,017.45 $30,017.45
5. Snow & Ice Control Bulk Rock Salt 267 Ton $33.28 $8,885.76 $8,885.76
6. Bank Charges Wire Transfers 5/21 & 10/16 2 $10.00 $20.00 $20.00
Total Maintenance $288,705.26
(Preliminary Engineering (See BLR-4310 and attached sheet for Fee Schedule) $11,649.49 $11,649.49
Total Estimated Maintenance Cost
$300,354.75
Submitted Janaury 20th 2004 Approved
By Mayor
Municipal Official Title District Engineer
Submit Four (4) Copies to District Engineer
2004